Ship Production Planning Using Shipbuilding System Modeling and Discrete Time Process Simulation

  • Yui Okubo
    Graduate School of Engineering Science, Yokohama National University, Yokohama 240-8501, Japan
  • Taiga Mitsuyuki
    Faculty of Engineering, Institute of Advanced Sciences, Yokohama National University, Yokohama 240-8501, Japan

説明

<jats:p>Production planning is an important factor for production efficiency in the shipyard. However, planning is currently executed by manual operations based on the experience of field workers because of the complexity of the target shipbuilding project. This paper proposes a method of creating a realistic production plan automatically by modeling the complex shipbuilding project and using the developed process simulation. Specifically, we propose a method to represent the target shipbuilding process by four system models—Product, Workflow, Workplace, and Team. By executing the developed process simulation using system models, a Gantt chart can be created as a realistic production plan. From the case studies of a virtual shipyard manufacturing a ship hull block, it can be said that the proposed method can create a good production plan considering the complexity of the target shipbuilding project. In addition, the proposed method can evaluate the bottleneck of the target shipyard and the re-allocation plan for workers quantitatively.</jats:p>

収録刊行物

被引用文献 (2)*注記

もっと見る

参考文献 (29)*注記

もっと見る

関連プロジェクト

もっと見る