工程順序が異なる場合の多ジョブのサイクリック・スケジューリング  工程のネットワークが閉路を含む場合

書誌事項

タイトル別名
  • Multi-job cyclic scheduling for a network with complicated processes (A case of process network having some loops)
  • コウテイ ジュンジョ ガ コトナル バアイ ノ タ ジョブ ノ サイクリック

この論文をさがす

説明

A multi-job cyclic scheduling problem, in which production processes of the jobs are various, was analyzed. In particular, a case of a process network having some loops was investigated. It was found that job's output interval between some cycles is constant at the steady state. This number of cycles was obtained. It was also shown that the branch-and-bound method is applicable to solving a job sequencing problem minimizing the job's output interval. A numerical example was demonstrated to clarify analytical results.