技術報告 342. 原子炉施設の廃止措置計画策定および管理のための計算システムの開発 東海発電所の解体作業に関するプロジェクト管理データの試算
書誌事項
- タイトル別名
-
- Development of Computer Systems for Planning and Management of Reactor Decommissioning. Estimation of Project Management Data on Dismantling Tokai Power Station.
- Estimation of Project Management Data on Dismantling Tokai Power Station
- 東海発電所の解体作業に関するプロジェクト管理データの試算
説明
Data on the Japan Power Demonstration Reactor dismantling activities were analyzed to be applied to planning and evaluation of decommissioning reactor facilities. These were then combined with the computer systems for planning and management of reactor decommissioning (COSMARD) as a database to estimate decommissioning project management data such as manpower needs and radiation exposure to workers. The Tokai Power Station decommissioning program, which will be conducted by the Japan Atomic Power Company as the first project on decommissioning a commercial nuclear power plant in Japan, was characterized by evaluating the project management data using COSMARD and the database. It was found from the study that COSMARD and unit productivity factors were applicable to planning and evaluation of reactor decommissioning programs.
収録刊行物
-
- 日本原子力学会誌
-
日本原子力学会誌 43 (5), 493-502, 2001
一般社団法人 日本原子力学会
- Tweet
キーワード
詳細情報 詳細情報について
-
- CRID
- 1390001206551274752
-
- NII論文ID
- 130003747529
-
- ISSN
- 21865256
- 00047120
-
- 本文言語コード
- ja
-
- データソース種別
-
- JaLC
- Crossref
- CiNii Articles
-
- 抄録ライセンスフラグ
- 使用不可