STUDY ON REAL-TIME FORECAST OF SEDIMENTATION IN RUN-OFF-RIVER HYDRO POWER PLANT

DOI

Bibliographic Information

Other Title
  • 流込み式水力発電所における出水時の土砂流入量予測モデルの構築について

Abstract

<p>Because the intakes of the run-off-river hydro power plants faces rivers, sediment in the riverbed flows in the waterway through the intakes when floods occurs. We developed a model to forecast sedimentation in the run-off-river hydro power plants. By this model, operators in the power plant can judge the stop of the water-intake to make damage with sedimentation a minimum.</p><p> This model is composed of three parts, the forecast of river discharge at the river by tank model, the forecast of total load at the river in front of the intake and the forecast of the ratio of sedimentation to total load in the river. Each model was constructed with results of 1-D and 2-D numerical analyses. We reproduced sedimentation of a hydraulic power plant in Okayama Prefecture from 2003 to 2008 by this model and compared the result with the observation data. This comparison showed that this model was able to reproduce the sedimentation process in this run-off-river hydro power plant</p>

Journal

Details 詳細情報について

  • CRID
    1390014282705718784
  • DOI
    10.11532/river.15.0_435
  • ISSN
    24366714
  • Text Lang
    ja
  • Data Source
    • JaLC
  • Abstract License Flag
    Allowed

Report a problem

Back to top