Multi-Project Planning with Time Constraints
-
- FUJII Susumu
- Faculty of Engineering, Kobe University
-
- MORITA Hiroshi
- Faculty of Engineering, Kobe University
-
- KANEDA Ken-ichi
- Chemical Process Development Institute, Kao Corporations
-
- MASAOKA Yoshinori
- Research and Development Center, Toshiba Corporations
Bibliographic Information
- Other Title
-
- 時間制約付きプロジェクト計画法
- ジカン セイヤク ツキ プロジェクト ケイカクホウ
Search this article
Description
We consider a multi-project scheduling problem with time constraints on resources, which appear in the planning of new projects that need to use the same resources as other projects under execution. We seek the optimal sequence of activities and the shortest completion time for all projects taken together. We propose a solution procedure using a branch and bound method for small size problems, where the bounding operations are established by a lower bound as well as an equivalence relation between the sequences of activities. An approximate solution by heuristics is required because of the high computational complexity. The approximate solutions obtained by eight heuristic rules are compared with the shortest completion times by using randomly generated simulating problems. We conclude that an earliest finishing time order rule provides effective heuristic rules for multi-project planning with time constraints on resources; however, a latest finishing time order rule is effective for a large-scale project.
Journal
-
- Transactions of the Institute of Systems, Control and Information Engineers
-
Transactions of the Institute of Systems, Control and Information Engineers 9 (1), 34-40, 1996
THE INSTITUTE OF SYSTEMS, CONTROL AND INFORMATION ENGINEERS (ISCIE)
- Tweet
Keywords
Details 詳細情報について
-
- CRID
- 1390282680141574400
-
- NII Article ID
- 10004335439
-
- NII Book ID
- AN1013280X
-
- ISSN
- 2185811X
- 13425668
- http://id.crossref.org/issn/00138444
-
- NDL BIB ID
- 3915470
-
- Data Source
-
- JaLC
- NDL
- Crossref
- CiNii Articles
-
- Abstract License Flag
- Disallowed