プレライニング工法による勝田台トンネルの施工
書誌事項
- タイトル別名
-
- THE CONSTRUCTION OF THE KATSUTADAI TUNNEL USING THE PRE-LINING METHOD
抄録
The pre-lining method was developped to stabilize the cutting face and decrease the surface settlement in the thin earth covered and uncohesive ground tunnel.<BR>This method was applied to the KATSUTADAItu nnel project having the above condition. The results were as follows:<BR>(1) Safe and satisfactory work was achieved because the groud surface settlement was controled under 40mm by the pre-lining.<BR>(2) The speed of the pre-lining work was 5-6 hours a cycle, the average excavation speed including the pre-lining work was 1.6m/day.