402 MRPとCRPを統合した作業日程計画のための製造リードタイム設定に関する研究(OS5 : 製造の見える化(1))

書誌事項

タイトル別名
  • 402 Study of production lead time offset for integrated operation schedule of MRP and CRP

抄録

Master production scheduling is the key information to synchronize all business units including production department and sales and marketing department. To make more effective and proactive, materials resource planning(MRP) and capacity resource planning (CRP) must be collaboratively performed in accordance with advanced planning and scheduling (APS) algorithms. In addition, it is necessary to have time buffer to protect from unexpected urgent orders, which disturb the resource usage and cause late deliveries. This paper proposes a calculation method for time buffer that is added to the normal production lead time. The proposed algorithm allows schedulers to make robust schedule for the manufacturing uncertainty.