Preoperational Test, Start-Up Tests and Operating Experience for Fukushima Daiichi Nuclear Power Station Unit-5
-
- INOUE Kazuo
- Nucl. Power Operation and Maintenance Dept., Tokyo Elec. Power Co.
Bibliographic Information
- Other Title
-
- 福島第1原子力発電所5号機の運転実績
- フクシマ ダイ 1 ゲンシリョク ハツデンショ 5ゴウキ ノ ウンテン ジッセ
Search this article
Abstract
Fukushima Daiichi Nuclear Power Station Unit-5(BWR 784 MWe) is located in Futaba-machi area north to Okuma-machi area where Unit-1--4 are located. Construction of this unit was started on Dec. 1971 before Unit-4 construction. Commercial operation was started on April 4, 1978 and keeps operation with no trouble. With completion of the unit, capacity of Tokyo Elec. Power Co. four nuclear power plants become 2, 812MWe, which is about 10% of whole Tepco's electric power plant's capacity. Here are the summary of the plant facility and the operating experience.
Journal
-
- Journal of the Atomic Energy Society of Japan / Atomic Energy Society of Japan
-
Journal of the Atomic Energy Society of Japan / Atomic Energy Society of Japan 21 (2), 160-164, 1979
Atomic Energy Society of Japan
- Tweet
Keywords
Details 詳細情報について
-
- CRID
- 1390282681528566144
-
- NII Article ID
- 130003909265
-
- NII Book ID
- AN00188477
-
- ISSN
- 21865256
- 00047120
-
- NDL BIB ID
- 2042742
-
- Text Lang
- ja
-
- Data Source
-
- JaLC
- NDL
- Crossref
- CiNii Articles
-
- Abstract License Flag
- Disallowed