RESTORATION OF A CABLE-STAYED BRIDGE DAMAGED BY THE 2016 KUMAMOTO EARTHQUAKE AND ESTIMATION OF STRUCTURAL STATE CHANGE AFTER THE RESTORATION

Bibliographic Information

Other Title
  • 熊本地震で被災した斜張橋の復旧対策と復旧後の状態変化の把握方法の提案

Abstract

<p> Two span continuous steel cable-stayed bridge “Kuwazuru Ohashi” was damaged by the 2016 Kumamoto earthquake, displacing whole girder, uplifting a girder end, twisting cables, inclining main tower, and so on. This paper proposes restoration of the bridge, replace of cables and displace of the girder utilizing monitoring, improvement of a bearing to redundant structure in order not to be damaged easily in the future. In addition, this paper proposed the method to estimate structural state change utilizing data due to tensile force and eigenfrequency to maintain the bridge after restoration.</p>